|
Interconnection Standard for Small Power
Producers
The purpose of this
bulletin is to set forth the administrative guidelines and
procedures to be used by cooperative personnel for
implementation of the Interconnection Standard for Small Power
Producers.
Metering and
Avoided Cost (Price paid by NLI for energy)
All
member-generators will be equipped with special bi-directional
metering. Bi-directional metering is specialized meters that
can measure and record the flow of power in two directions.
This type of metering is capable of measuring both the
electrical power used by the member (kWh in) and any excess
power generated back (kWh out) to NLI’s electrical supply
system. These meters will be equipped with a detent device or
equivalent to prevent reverse operation. Additional metering
for kVA and kVAr will be determined by the requirements of the
individual installation. Any special metering required which
is more than the typical NLI house meter (form 2S) will be
installed at the member’s expense.
The kilowatt-hours
(kWh) supplied by the cooperative to the member and the
kilowatt-hours (kWh) supplied by the member-generator to the
cooperative will be recorded each month. The net energy
supplied to NLI’s electric system shall be multiplied times
NLI’s avoided cost with the amount credited on the member’s
next bill.
In December of each
year, after the November billing, any net credit balance on
the account of the member-generator shall be cleared by
issuing a check in the amount of the credit balance to the
member-generator.
The net energy is
the difference between electrical energy consumed by the
member from NLI’s electrical supply system and the electrical
energy generated by the member and fed back into NLI’s
electrical supply system.
The avoided cost
shall be defined as a weighted average of the monthly BPA PF
rates including any cost recovery additions that BPA
includes. The average will be weighted between heavy load
hours, 60 percent (0.60) and low load hours 40 percent (0.40).
The avoided cost for
the period from April 1, 2007 to September 30, 2007 will be
based upon the following figures:
Month
$/kWh HLH $/kWh LLH
Apr
2007
0.02495 0.01793
May
2007 0.02084
0.01441
June
2007 0.01887
0.01002
July
2007 0.02324
0.01701
Aug
2007 0.02721
0.02018
Sept
2007 0.02809
0.02254
Therefore for the
period from April 1, 2007 to September 30, 2007 the avoided
cost paid to member-generators for the net energy supplied to
the NLI system will be $0.02113 per kilowatt-hour.
Technical
The requirements for
this class are based upon a low density of parallel generation
on the NLI circuits. Additional conditions or restrictions
may be imposed on existing or new generators if the density
exceeds a tolerable limit or 1 per cent of NLI’s total system
peak demand requirement.
The member’s
generation facility will have a maximum output of twenty-five
kilowatts (25kW). The facility shall be located on the
member’s premises, will operate in parallel with NLI’s
electric power system and is intended primarily to offset part
of the member’s own electric power requirements presently
supplied by NLI.
The member will
supply NLI with the information required in the Small
Generation Interconnection Agreement Exhibit A. No
modifications or revision to the member’s installation should
be made without prior notification and approval by NLI.
The member shall
provide the electrical interconnection on the member’s side of
the meter. At the member’s expense, NLI shall make reasonable
modifications to NLI’s electrical system to accommodate the
generation facility. Modifications to NLI’s system will be
billed at NLI’s actual cost. NLI will provide a cost estimate
before the work is started. Estimated costs shall be received
by NLI in advance of the start of any work on the system.
After the project accounting has been completed, if the costs
are under the estimate the difference will be refunded to the
member; if the costs are over the estimate the member will pay
this additional cost incurred to NLI.
Except for the
bi-directional metering equipment owned and maintained by NLI,
all the equipment on the member’s side of the meter, including
the required disconnecting switch, shall be provided and
maintained in satisfactory operating condition by the member
and shall remain the property and responsibility of the
member. NLI shall bear no liability for the member’s
equipment or its operation.
At the member’s
expense, the generation facility shall include all equipment
necessary to meet applicable safety, power quality and
interconnection requirements of NLI. The electrical facility
shall be designed and installed in accordance with prudent
electrical industry practices and applicable portions of the
latest edition of the National Electrical Safety Code (NESC),
the National Electrical Code (NEC), Institute of Electrical
and Electronics Engineers (IEEE) and Underwriters Laboratories
(UL).
The member shall
furnish and install a manual disconnect device capable of
fully disconnecting and isolating the generation facility from
NLI’s electrical system. The disconnect device will be of the
visible break type in a metal enclosure. The disconnect
device will be located next to NLI’s meter, between the meter
and the generation. This device will enable NLI to disconnect
the member’s generation from NLI’s electric system for
personnel safety while working on the co-op’s equipment. This
disconnect must be accessible by NLI personnel 24 hours a day
and have the provision for NLI to padlock the switch in the
open position.
The member shall
furnish, install, operate and maintain in good order and
repair all equipment required for the safe operation of the
generation operating in parallel with NLI’s electrical
system. This shall include, but not be limited to, equipment
necessary to (1) establish and maintain automatic synchronism
with NLI’s electric system; (2) automatically disconnect the
generation from NLI’s electrical system in the event of
overload or outage on NLI’s electrical system; (3) prevent the
generation from being connected to or attempt to close onto a
de-energized or single-phased (if normally three-phase) NLI
electrical system.
Typical protection
devices, which may be required to satisfy the above
requirements, are:
Phase
overcurrent relays. (50/51)
In certain cases
these will have to be voltage-restrained or voltage-controlled
to provide coordination with NLI’s protective devices.
Residual overcurrent
or overvoltage relays to trip for ground faults. (51N or 59N)
Under/over voltage
relays. (27/59)
Under/over frequency
relays. (81)
Phase sequence/undervoltage
relay. (47/27)
To
permit paralleling when the voltage and phase sequence are
normal.
The member’s
generation system shall not introduce harmonics into the
cooperative’s electrical system that are excessive enough to
affect other members. Present industry practice is to limit
total voltage harmonic distortion to less than 5% THD.
However, any interference to the electrical or communications
systems (to include telephone, radio, television, carrier,
etc.) resulting from the member’s equipment, will be grounds
for termination of the interconnection until the member
corrects the condition in the generation system to the
satisfaction of NLI. This correction may require the
installation of filters to bring the harmonic output to an
acceptable level.
At NLI’s request,
the member shall provide and pay for a phone line to be used
for communications between NLI’s main office and the
bi-directional metering at the member’s facility. This phone
line will be used for automated meter reading where required.
NLI has the right to request this phone line as long as the
Small Generation Interconnection Agreement is in force. (This
phone line may be the same line as the member’s personal
phone.)
NLI has the right to
review the installation prior to energization. The member
will correct any deficiencies noted in the interconnection
equipment prior to energization. This review by the
cooperative will not be an inspection or check of the member’s
equipment and will not relieve the owner of any liability.
Insurance
The member agrees to
maintain, at their own cost and expense, general liability
insurance relating to their generation operations for the life
of the connection to NLI. This policy shall name NLI as
insured and be in the amount of $200,000.
Prior to
energization of the facility and on each anniversary of the
signed Agreement, the member shall provide NLI properly
executed and current certificates of insurance with respect to
all insurance policies required to be maintained for this
Agreement. Certificates of insurance shall provide the
following information:
Name of insurance
company, policy number and expiration date. The coverage
required and the limits on each, including the amount of
deductibles or self-insured retentions.
A statement
indicating that NLI shall receive at least thirty (30) days
prior written notice of cancellation or expiration of a
policy, or reduction of liability limits with respect to a
policy.
At NLI’s request, in
addition to the foregoing certifications, the member shall
deliver to NLI a copy of applicable sections of each insurance
policy.
Once a year the
Administrative Bulletin may be reviewed and the minimum
coverage limits for the liability insurance may be adjusted by
NLI at its sole option. NLI shall give at least thirty (30)
days notice of its election to increase the minimum coverage
limits
Interconnection
Agreement
The member-generator
will be required to sign the Small Generation Interconnection
Agreement before Northern Lights will accept delivery of the
energy.
Authorized
NLI employees shall have the right to enter the member’s
property at any time, with or without notice, for the purpose
of observing and/or testing the interconnection, disconnecting
device and bi-directional metering equipment. |