Northern Lights, Inc
Lake Creek Project, FERC Project No. 2594

Integrated Licensing Process Plan [*]
Responsible Entity Pre-License Application Schedule Milestones Ferc Regulation
NLIMail Pre-Application Document (PAD) Questionaire to Agencies and Stakeholders 5/31/2005 
ParticipantsReturn Questionaire to NLI 6/15/2005 
NLIHold Public Informational Meetings 7/12 & 13/2005 
NLIBegin PAD Preparation 7/15/20055.6
NLIRequest FERC Designate NLI as Non-Federal Representative for Section 106 Consultation 7/15/20055.5(e)
NLIRequest FERC Designate NLI as Non-Federal Representative for ESA Consultation 7/15/20055.5(e)
FERCDesignate NLI as Non-Federal Representative for Section 106 and ESA Consultation 8/15/20055.5(e)
NLIFile Notice of Intent (NOI) and PAD (w/in 5.5 years of license expiration) 5/30/20065.5 & 5.6
NLIIssue Public Notice of NOI/PAD 5/30/20065.3(d)(2)
FERCHold Tribal Meetings (if any) (w/in 30 days of NOI) 6/29/20065.7
FERCIssue FERC Notice of Proceeding; Issue Scoping Document 1 (SD1) (w/in 60 days of NOI) 6/29/20065.8(a)(c)
FERCHold Site Visit and Scoping Meetings (w/in 30 days of FERC Notice of Proceeding) 7/25 & 26/20065.8(b)(3)(viii)
ParticipantsFile Comments on PAD/SD1 and STUDY REQUESTS (w/in 60 days of FERC Notice of Proceeding) 8/28/20065.9(a)(b)
FERCIssue Scoping Document 2 (w/in 45 days of SD1 comments) None [¹] 5.1
NLIFile Proposed Study Plan (PSP) (w/in 45 days of PAD comments) 10/12/20065.11(a)
NLIHold PSP Initial Meeting with Participants (w/in 30 days of PSP) 11/7 & 8/20065.11(e)
ParticipantsFile Comments on PSP (w/in 90 days of PSP) 1/10/20075.12
NLIFile Revised Study Plan (RSP) (w/in 30 days of PSP comments) 2/9/20075.13(a)
ParticipantsFile Comments on RSP (w/in 15 days of RSP) 2/26/20075.13(b)
FERCIssue Study Plan Determination (SPD) (w/in 30 days of RSP) 3/9/20075.13(c)
MDEQ [2] File any Study Disputes (w/in 20 days of SPD) 3/29/20075.14(a)
Dispute Resolution PanelDispute Resolution Panel Convenes (w/in 20 days of dispute) 4/18/20075.14(d)
NLIFile Comments and Information Regarding Dispute (w/in 25 days of dispute) 4/23/20075.14(i)
Dispute Resolution PanelDispute Resolution Panel Technical Conference 4/24/20075.14(j)
Dispute Resolution PanelIssue Dispute Recommendations (w/in 50 days of dispute) 5/18/20075.14(k)
FERCIssue Director's Study Dispute Determination (w/in 70 days of dispute) 6/7/20075.14(l)
NLIFirst Study Season 20075.15
NLIFile Initial Study Report (w/in 1 year of SPD) 11/13/20075.15(c)(1)
NLIHold Initial Study Report Meeting (w/in 15 days of Initial Study Report) 11/28/20075.15(c)(2)
NLIFile Initial Study Report Meeting Summary/Changes to Study Plan (w/in 15 days of Initial Study Report Meeting) 12/14/20075.15(c)(3)
ParticipantsFile Any Study Plan Disputes/Amendment Requests (w/in 30 days of Initial Study Report Meeting Summary) 1/12/20085.15(c)(4)
ParticipantsFile Responses to any Study Plan Disputes/Amendment Requests (w/in 30 days of any Disputes/Amendment Requests) 2/13/20085.15(c)(5)
FERCIssue Director's Determination on any Study Plan Disputes/Amendment Requests (w/in 30 days of Responses) 3/14/20085.15(c)(6)
NLISecond Study Season 20085.15
NLIFile Updated Study Report and Notice of Intent to File a Draft License Application (DLA) (w/in 2 years of SPD) 11/10/20085.15(f) & 5.16(c)
NLIHold Updated Study Report Meeting (w/in 15 days of Updated Study Report) 11/25/20085.15(f)
NLIFile Updated Study Report Meeting Summary/Changes to Study Plan (w/in 15 days of Updated Study Report Meeting) 12/10/20085.15(f)
ParticipantsFile any Study Plan Disputes/Amendment Requests (w/in 30 days of Updated Study Report Meeting Summary) 1/9/20095.15(f)
NLIFile Responses to any Study Plan Disputes/Amendment Requests (w/in 30 days of any Disputes/Amendment Requests) 2/9/20095.15(f)
FERCIssue Director's Determination on any Study Plan Disputes/Amendment Requests (w/in 30 days of Responses) 3/10/20095.15(f)
NLIFile Draft License Application (DLA), draft Biological Assessment (if any), and draft Historic Properties Management Plan (if any) (no later than 150 days prior to Final License Application) 7/1/20095.16(a)(b)
ParticipantsFile Comments on DLA (w/in 90 days of DLA) 9/29/20095.16(e)
NLIFile Final License Application (FLA) (w/in 24 months of license expiration) [3] 11/23/20095.17(a)
NLIRequest Water Quality Certificate (WQC) from MDEQ (w/in 60 days of REA notice) 11/23/2009 
NLIIssue Notice of FLA (TWICE no later than 14 days of FLA) 11/23/20095.17(d)(2)
FERCIssue Notice of FLA (w/in 14 days of FLA) 12/1/20095.19(a)
FERCIssue Director's Determination on any Additional Study Requests and Notification of any Deficiencies (w/in 30 days of FLA) 12/23/20095.19(d) 5.20(a)(2)
MDEQIssue Decision on Adequacy of WQC Application 12/23/2009N/A
FERCIssue FERC Acceptance Notice and Ready for Environmental Analysis (REA) Notice 3/1/20105.22
ParticipantsFile Comments, Interventions and 10(a) Recommendations (w/in 60 days of FERC Acceptance Notice) 5/1/20105.23(a)
FWS, MFWPFile 10(j) Recommendations 5/1/20105.23(a)
FERCIssue Single Environmental Assessment (EA) [4]; Issue Biological Assessment [5] (if any); Issue draft Programmatic Agreement for Historic Properties (if any) 9/1/20105.24(a)
ParticipantsFile Comments on EA (w/in 30 days of EA) 10/1/20105.24(c)
MDEQIssue Tentative WQC with Schedule for Final WQC 10/1/2010N/A
MDEQHold Public Hearing on Tentative WQC (if any) 10/15/2010N/A
MDEQIssue Final WQC 11/1/2010N/A
FWSIssue Biological Opinion (if any) 1/15/2011N/A
FERCIssue any New License Order 3/15/2011FPA

* Last Revised On 7/7/05

  1. At this time, FERC does not proposed issuing a SD2.
  2. Shaded milestones are unnecessary if no disputes.
  3. A license application must be filed by 11/30/09 (current license expires 11/30/11).
  4. FERC will likely issue a "Single EA" (without a draft EA).
  5. FERC will likely incorporate its Biological Assessment into its Single EA (a separate document would not be issued).