Notes from Public Informational Meetings (July 12-13, 2005)
1.0
Introduction
Northern Lights Inc. (NLI), an
Electric Cooperative based in Sagle, Idaho, is preparing to relicense its Lake
Creek Hydroelectric Project, FERC Project No. 2594 (Project). The Project is
licensed by the Federal Energy Regulatory Commission (FERC); the current
license expires on November 30, 2011. The Project is located on Lake Creek near
Troy in Lincoln County, Montana. Electricity generated by this facility
serves NLI's customers in Montana, northern Idaho, and eastern Washington.
NLI is using FERC's Integrated
Licensing Process (ILP) to relicense the Project. NLI held a series of public
forums to kick off the process on July 12 and 13 to explain relicensing, describe
the Project, and provide an opportunity for agencies, tribes and other
interested parties to provide information they may have about the Project.
Each forum was opened by NLI's
Operations Manager, Mark Contor, who gave a short introduction. Jay Maher of
Kleinschmidt Associates then gave a brief presentation detailing the project
features and outlining the relicensing process. Elisabeth Blaug of FERC then
gave a presentation explaining the ILP and FERC's role. Mark and Jay then
described project operations and answered questions. Specific details from each
public forum are provided below.
2.0
Libby Meeting
| LOCATION: |
Libby, MT |
| DATE AND TIME: |
July 12, 2005 9:0011:00 am |
| ATTENDEES: |
- Mark Contor NLI
- Elisabeth Blaug FERC
- Jay Maher Kleinschmidt
Associates
- Randy
Dorman Kleinschmidt Associates
- Larry Coryell
- Mike Hensler Montana
Fish, Wildlife, and Parks
- Christian Levine
Montana Department of Environmental Quality
- Glenn Phillips Montana
Fish, Wildlife, and Parks
- Wilfried Raab
- John Vignali Tungsten
Holdings
|
During the question and answer
session of the meeting Glenn Phillips noted an additional comprehensive plan
that should be added to the list: a comprehensive habitat plan developed by
Montana Fish, Wildlife, and Parks (MFWP) for the U. S. Fish and Wildlife
Service.
The group discussed possible sediment
contamination from upstream mining in the impoundment. Mark noted that NLI had
conducted a sediment sampling study several years ago and found no
contamination in lake sediments or in the spoils piles left from dredging
conducted by a previous owner. Glenn expressed MFWP's concern regarding large
sediment releases from the Project in the past, and Mark said that these
releases were due to the previous project owner periodically opening the deep
gates to flush out sediment in the impoundment. However, Mark noted that NLI
had not been following this practice since they took over ownership and did not
intend to do so in the future.
Mike Hensler noted a potential concern about
bull trout entrainment and impingement, and asked about the spacing of trashracks.
Mark will follow-up on the specifics of spacing. Mark described the frequency
of trashraking: perhaps twice a day or so during a low-debris month like
August, and as much as 812 times a day in the spring.
Glenn and Mark also noted that while current
conditions preclude upstream fish passage above the 40-ft high falls below the
project, a colleague in MFWP had speculated that passage might be possible
under higher flow conditions.
The group then discussed public fishing. Mark
explained that currently anglers may park at the entrance to the powerhouses
and walk down to a location below the Project tailrace. Signage is in place but
an old railing has been removed due to safety concerns. No known creel study
has been conducted on Lake Creek. Mike noted that Lake Creek is the only location
in the basin with brown trout.
In closing several state agency members
suggested that future meetings might be held in Kalispell, which would be a
more central location for several participants. Wilfried Raab asked not to be
added to the mailing list.
3.0
Site Visit
| LOCATION: |
Troy, MT |
| DATE AND TIME: |
July 12, 2005 2:004:00 pm |
| ATTENDEES: |
- Mark Contor NLI
- Elisabeth Blaug FERC
- Jay Maher Kleinschmidt
Associates
- Randy
Dorman Kleinschmidt Associates
- Larry Coryell
|
During the site visit attendees
toured both power houses and then walked up the creek bed. The group then
walked the top of the dam and down along the length of the penstock. Some
members of the group also descended into the ravine to see the waterfalls below
the dam.
| LOCATION: |
Troy, MT |
| DATE AND TIME: |
July 12, 2005 7:009:00 pm |
| ATTENDEES: |
- Mark Contor NLI
- Elisabeth Blaug FERC
- Jay Maher Kleinschmidt
Associates
- Randy
Dorman Kleinschmidt Associates
- Gary Managhan
- Lana Managhan
- Evelyn Fagg
|
Following the presentations Gary
and Lana Managhan noted that the impoundment is frequently used by a small
group of local fisherman who must cross the Managhan's property to access the
impoundment. Fish species known to be found in the impoundment include
cutthroat trout, and brown trout.
Gary also mentioned that while
permitting his gravel pit (near but not immediately adjacent to the Project
Boundary) the Montana Department of Environmental Quality noted that bull trout
do not spawn that far downstream in the drainage. Gary also indicated that
there should be a number of documents available from the DEQ related to the
permitting of his operation and any potential environmental effects on Lake
Creek. NLI will follow-up with DEQ.
Gary, Lana, and Evelyn all expressed
satisfaction with current Project operations and expressed concern if there
were to be any changes to the existing operational regime.
5.0
Sagle Meeting
| LOCATION: |
Sagle, ID |
| DATE AND TIME: |
July 13, 2005 7:009:00 pm |
| ATTENDEES: |
- Mark Contor NLI
- Elisabeth Blaug FERC
- Jay Maher Kleinschmidt
Associates
- Randy
Dorman Kleinschmidt Associates
- Betty Kinne
|
Following the presentation Betty Kinne
asked to be added to the mailing list for the Lake Creek relicensing.
6.0
Meeting Materials
The following presentations and
handouts were provided during the three meeting and are attached to these
notes:
|