FERC Order Issuing Lake Creek License

[62,439]

Montana Light and Power Company, Project No. 2594-001

Order Issuing License (Major)

(Issued December 16, 1981)

William W. Lindsay, Director, Office of Electric Power Regulation

            Montana Light and Power Company (Applicant) filed on November 25, 1980, an application for a license under Part I of the Federal Power Act (Act) for its constructed Lake Creek Project, FERC No. 2594 located on Lake Creek, in Lincoln County, Montana.1

            Notice of the application has been published and comments have been received from Federal, state, and local agencies.  No protests or petitions to intervene have been filed, and none of the commenting agencies objected to issuance of this license.2 

Project Description and History

            The constructed Lake Creek Project consists of a 34-foot high dam, a 150-acre-foot reservoir, water conduits, two powerhouses with a total rated capacity of 4.5 MW , and associated transmission facilities. The project is more fully described in Ordering Paragraph (B) of this order.  A major portion of the project, including one of the powerhouses with an installed capacity of 1 MW, was built in 1916-1917 and was acquired by the Applicant in 1922. A second powerhouse with an installed capacity of 3.5 MW and its appurtenant facilities were built in 1948-1949. The Applicant originally filed an application for license for the project on May 3, 1966, with a disclaimer of jurisdiction and requested that the Commission issue a declaratory order finding it has no jurisdiction over the project. Staff found the application deficient and requested the Applicant to correct the deficiencies. The Applicant did not correct the deficiencies and on May 30, 1980, the application was rejected. The Applicant, however, was afforded another opportunity to file a license application under the new regulations governing applications for license for Major Projects at Existing Dam (Order No.59, issued November 19, 1979). It was also determined that if a license application which conforms to the new regulations were filed within 6 months from May 30, 1980, the Commission would grant a 30-year term license for the project instead of the normal 2O-year term and would relieve the Applicant of approximately one-half of the back annual charges that otherwise would be due for the project. Articles 26 and 27 require payment of back annual charges.

Jurisdiction

            Staff has found that the Lake Creek Project is connected with Pacific Power and Light Company's (PP&L) Libby system at a tie point near Libby, Montana. PP&L's power requirements for the Libby system, excluding dump power purchases from the Applicant, are transmitted into Montana from Idaho over facilities of the Bonneville Power Administration. It is determined, therefore, that the power generated at Lake Creek Project affects interstate commerce within the meaning of Section 23(b) of the Act by virtue of its inter-connection with PP&L's system.

            Applicant states that the oldest and major portion of the project was built in 1916-17 and was acquired by the Applicant in 1922. The second powerhouse, with an installed capacity of 3,500 kW, and an associated penstock were built in 1948-49. It is, therefore, concluded that there has been substantial post-1935 construction at the project.

            In accordance with the Supreme Court's interpretation of the Act in the Taum Sauk3 and Farmington4 decisions, it is concluded that The Montana Light and Power Company's Lake Creek Project is subject to the Commission's licensing authority under the Federal Power Act.

Safety and Adequacy

             Stability of project structures under normal and extreme loading conditions has been analyzed. The Lake Creek Dam is considered safe under normal loading conditions. The dam is not safe under Probable Maximum Flood conditions, but failure of the structure during such an extreme event would not present a hazard to downstream life or cause significant property damage due to the project's negligible storage capacity (150 acre-feet) and its remote location.5 Therefore, no remedial work is required. It is concluded that the project, under the conditions of this license, is safe and adequate.

 Recreation Resources

            No recreational facilities have been constructed, for reasons of safety, small reservoir size, low recreational value, and because there are considerably more desirable recreational opportunities available in the vicinity. However, fishing is permitted. The application includes letters from both (1) the Montana Department of Fish, Wildlife, and Parks and (2) the Heritage Conservation and Recreation Service indicating that the installation of recreational facilities is not warranted at this time. Should recreational facilities be required  in the future, Article 17 of the Standard Form L-10, included in this license, requires the licensee to provide appropriate recreational facilities.

Water Quality

            Montana Department of Health and Environmental Sciences certified that pursuant to Section 401 of the Federal Water Pollution Control Act, the continued operation of the Lake Creek Project would not violate Montana's water quality standards.

Spoil Area

            The Applicant has started a program of silt removal from the reservoir which should be completed in the near future. The silt is being deposited on land within the project boundary. The U.S. Department of the Interior (Interior) indicated that the spoil should be graded and seeded with native forest plant species when the silt-removal program is completed. Applicant concurs with Interior and stated that silt removed from the reservoir will be landscaped in a manner consistent with recommendations contained in letters from the Soil Conservation Service and the U.S. Fish and Wildlife Service.

Cultural Resources

            No properties on or eligible for the National Register of Historic Places would be impacted by continued operation of the project or by silt removal activities. In accordance with standard Commission practice,6 Article 29 is being included in the license to ensure that cultural resources protection measures would be implemented in the event of any future construction or ground-disturbing activity at the project.

Environmental Impacts

             The project has been in continuous operation for over 50 years. Any adverse effects associated with its construction have stabilized. Applicant does not propose any new construction or changes in the project's operation. Any adverse environmental impacts resulting from completion of the silt removal program would be of short-term duration. The spoil area would be landscaped and seeded with native forest plant species. For these reasons, it is concluded that approval of the license application would not constitute a major Federal action significantly affecting the quality of the human environment.

Comprehensive Development

            The run-of-the-river project makes efficient use of water flow and fall of the creek and is not in conflict with any existing or planned development in the river basin. Continued operation of this project provides 4500 kW of installed capacity capable of an average annual generation of 23.4 million kWhs, and uses a renewable resource that saves the equivalent of approximately 38,400 barrels of oil or 11,000 tons of coal per year.

            It is concluded that, as conditioned in this license, Project No. 2594 is best adapted to a comprehensive plan for development of Lake Creek basin for beneficial public uses and that issuance of this license is in the public interest.

License Term and Annual Charges

            Under the Commission's policy and as explained previously under "Project Description and History", this license would have been made effective January 1, 1948, the year that post-1935 construction first occurred. Because of the 50-year maximum statutory license period, however; and the Commission's incentive program resulting in the issuance of a license for 30 years this license will be made effective December 1, 1961. Payment of one- half of back annual charges will be based upon that effective date, but this license will also be conditioned upon payment of an amount equivalent to one-half the annual charges that would otherwise have been due for the period from January 1, 1948 to November 30, 1961.

It is ordered that:

            (A) This license is issued to Montana Light and Power Company (Licensee) of Libby, Montana, under Part I of the Federal Power Act for a period effective December 1, 1961, and terminating November 30, 2011, for the continued operation and maintenance of Lake Creek Project No.2594, located in Lincoln County, Montana, on Lake Creek and affecting the interests of interstate commerce. This license is subject to the terms and conditions of the Act, which is incorporated by reference as part of this license, and subject to the regulations the Commission issues under the provisions of the Act.

            (B) The Lake Creek project No.2594 consists of:

            (1) All lands, to the extent of the Licensee's interests in those lands, constituting the project area and enclosed by the project boundary .The project area and boundary are shown and described by certain exhibits that form part of the application for license and that are designated and described as: .

                   Exhibit                     FERC No.                               Showing

                    G-1                          2594-9                                  General Map

                    G-2                          2594-10                                General Map

            (2) Project works consisting of:   (1) a 268-foot long, 34-foot high concrete gravity dam creating; (2) a reservoir with a storage capacity of 150 acre-feet; (3) a reinforced concrete intake structure; (4) a 1,694-foot long, 10-foot diameter flume leading to; (5) a forebay created by a reinforced concrete structure with wood superstructure; (6) a 297-foot long, 5-foot diameter penstock leading to; (7) Powerhouse #1 containing a Francis- type, turbine-generating Unit with a rated capacity of 1 MW; (8) a second penstock 441 feet long with a diameter of 8.5 feet leading to: (9) Powerhouse #2 containing a Francis-type, turbine-generating unit with a rated capacity of 3.5 MW; and (10) a 2,4-kV generator lead, a 7.2-kV generator lead, a 7.2/34.5-kV step-up transformer at Powerhouse #2, a 150-foot long, 7.2-kV transmission line, a l00 foot long, 34.5-kV transmission line and appurtenant facilities.

            The location, nature, and character of these project works are generally shown and described by the exhibits cited above and more specifically shown and described by certain other, exhibits that also form a part of the application for license and that are designated and described as:

            Exhibits                       FERC No.                               Showing

            F-1                              2594-7                                     Powerplants and Forebay

            F-2                              2594-8                                     Lake Creek Dam

            (3) All of these structures, fixtures, equipment, or facilities used or useful in the operation or maintenance of the project and located within the project boundary, all portable property that may be employed in connection with the project, located within or outside the project boundary, as approved by the Commission, and all riparian or other rights that are necessary or appropriate in the operation or maintenance of the project.

            (C) Exhibits F and G designated in ordering paragraph (B) above are approved and made a part of the license.

            (D) This license is also subject to the terms and conditions set forth in Form L-10 (revised October, 1975), entitled "Terms and Conditions of License for Constructed Major Project Affecting the Interests of Interstate or Foreign Commerce," attached to (See 54 FPC 1858) and made a part of this license. The license is also subject to the following additional articles:

            Article 24. (a) In accordance with the provisions of this article, the Licensee shall have the authority to grant permission for certain types of use and occupancy of project lands and waters and to convey certain interests in project lands and waters for certain other types of use and occupancy, without prior Commission approval. The Licensee may exercise the authority only if the proposed use and occupancy is consistent with the purposes of protecting and enhancing the scenic recreational, and other environmental values of the project. For those purposes, the Licensee shall also have continuing responsibility to supervise and control the uses and occupancies for which it grants permission, and to monitor the use of, and ensure compliance with the covenants of the instrument of conveyance for, any interests that it has conveyed, under this article. If a permitted use and occupancy violates any condition of this article or any other condition imposed by the Licensee for protection and enhancement of the project's scenic, recreational, or other environmental values, or if a covenant of a conveyance made under the authority of this article is violated, the Licensee shall take any lawful action necessary to correct the violation. For a permitted use or occupancy, that action includes, if necessary, canceling the permission to use and occupy the project lands and waters and requiring the removal of any non-complying structures and facilities.

            (b) The types of use and occupancy of project lands and waters for which the Licensee may grant permission without prior Commission approval are: (1) landscape plantings; (2) non-commercial piers, landings, boat docks, or similar structures and facilities; and (3) embankments, bulkheads, retaining walls, or similar structures for erosion control to protect the existing shoreline. To the extent feasible and desirable to protect and enhance the project's scenic, recreational, and other environmental values, the Licensee shall require multiple use and occupancy of facilities for access to project lands or waters. The Licensee shall also ensure, to the satisfaction of the Commission's authorized representative, that the uses and occupancies for which it grants permission are maintained in good repair and comply with applicable State and local health and safety requirements. Before granting permission for construction of bulkheads or retaining walls, the Licensee shall: (1) inspect the site of the proposed construction, (2) consider whether the planting of vegetation or the use of riprap would be adequate to control erosion at the site, and (3) determine that the proposed construction is needed and would not change the basic contour of the reservoir shoreline. To implement this paragraph (b), the Licensee may, among other things, establish a program for issuing permits for the specified types of use and occupancy of project lands and waters, which may be subject to the payment of a reasonable fee to cover the Licensee's costs of administering the permit program. The Commission reserves the right to require the Licensee to file a description of its standards, guidelines, and procedures for implementing this paragraph (b) and to require modifications of those standards, guidelines, or procedures.

            (c) The Licensee may convey easements or rights-of-way across, or leases of, project lands for: (1) replacement, expansion, realignment, or maintenance of bridges and roads for which all necessary State and Federal approvals have been obtained; (2) storm drains and water mains; (3) sewers that do not discharge into project waters; (4) minor access roads; (5) telephone, gas, and electric utility distribution lines; (6) non-project overhead electric transmission lines that do not require erection of support structures within the project boundary; (7) submarine, overhead, or underground major telephone distribution cables or major electric distribution lines (69-kV or less); and (8) water intake or pumping facilities that do not extract more than one million gallons per day from a project reservoir. No later than January 31 of each year, the Licensee shall file three copies of a report briefly describing each conveyance made under this paragraph (c) during the prior calendar year, the type of interest conveyed, the location of the lands subject to the conveyance, and the nature of the use for which the interest was conveyed.

            (d) The Licensee may convey fee title to, easements or rights-of-way across, or teases of project lands for: (1) construction of new bridges or roads for which all necessary State and Federal approvals have been obtained; (2) sewer or effluent lines that discharge into project waters, for which all necessary Federal and State water quality certificates or permits have been obtained; (3) other pipelines that cross project lands or waters but do not discharge into project waters; (4) non-project overhead electric transmission lines that require erection of support structures within the project boundary, for which all necessary Federal and State approvals have been obtained; {5) private or public marinas that can accommodate no more than 10 watercraft at a time and are located at least one-half mile from any other private or public marina; (6) recreational development consistent with an approved Exhibit R or approved report on recreational resources of an Exhibit E; and (7) other uses, if: (i) the amount of land conveyed for a particular use is five acres or less; (ii) all of the land conveyed is located at least 75 feet, measured horizontally, from the edge of the project reservoir at normal maximum surface elevation: and (iii) no more than 50 total acres of project lands for each project development are conveyed under this clause (d) (7) in any calendar year. At least 45 days before conveying any interest in project lands under this paragraph (d), the Licensee must file a letter to the Director, Office of Electric Power Regulation, stating its intent to convey the interest and briefly describing the type of interest and location of the lands to be conveyed (a marked Exhibit G or K map may be used). the nature of the proposed use, the identity of any Federal or State agency official consulted, and any Federal or State approvals required for the proposed use. Unless the Director, within 45 days from the filing date, requires the Licensee to file an application for prior approval, the Licensee may convey the intended interest at the end of that period.

            (e) The following additional conditions apply to any intended conveyance under paragraphs (c) or (d) of this article:

            (1) Before conveying the interest, the Licensee shall consult with Federal and state fish and wildlife or recreation agencies, as appropriate, and the State Historic Preservation Officer.

            (2) Before conveying the interest, the Licensee shall determine that the proposed use of the lands to be conveyed is not inconsistent with any approved Exhibit R or approved report on recreational resources of an Exhibit E; or, if the project does not have an approved Exhibit R or approved report on recreational resources, that the lands to be conveyed do not have recreational value.

            (3) The instrument of conveyance must include covenants running with the land adequate to ensure that: (i) the use of the lands conveyed shall not endanger health, create a nuisance, or otherwise be incompatible with overall project recreational use; and (ii) the grantee shall take all reasonable precautions to ensure that the construction, operation, and maintenance of structures or facilities on the conveyed lands will occur in, a manner that will protect the scenic, recreational, and environmental values of the project.

            (4) The Commission reserves the right to require the Licensee to take reasonable remedial action to correct any violation of the terms and conditions of this article, for the protection and enhancement of the project's scenic, recreational, and other environmental values. 

            (f) The conveyance of an interest in project lands under this article does not in itself change the project boundaries. The project boundaries may be changed to exclude land conveyed under this article only upon approval of revised Exhibit G or K drawings (project boundary maps) reflecting exclusion of' that land. Lands conveyed under this article will be excluded from the project only upon a determination that the lands are not necessary for project purposes, such as operation and maintenance, flowage, recreation, public access, protection of environmental resources, and shoreline control, including shoreline aesthetic values. Absent extraordinary circumstances, proposals to exclude lands conveyed under this article from the project shall be consolidated for consideration when revised Exhibit G or K drawings would be filed for approval for other purposes.

            Article 25. The Licensee shall pay the United States the following annual charge, effective the first day of the month following issuance of this license:

            For the purpose of reimbursing the United States for the cost of administration of Part I of the Act, a reasonable amount as determined in accordance with the provisions of the Commission's regulations in effect from time to time. The authorized installed capacity for that purpose is 6,000 horsepower .

            Article 26. The Licensee shall pay, the Untied States an amount equal to one-half of the following annual charge that would have been applied for the period December 1, 1961, to the last day of the month in which this license is issued:

            For the purpose of reimbursing the United States for the cost of administration of Part I of the Act, a reasonable annual charge as determined by the Commission in accordance with the applicable provisions of its regulations. The authorized installed capacity for such purposes is 6,000 horsepower.

            Article 27. The Licensee shall pay the United States an amount equal to one-half of the following annual charge that would have been applied for the period January 1, 1948, to November 30, 1961, if the project had been licensed during that period:

            For the purpose of reimbursing the United States for the cost of administration of Part 1 of the Act, a reasonable annual charge as determined by the Commission in accordance with the applicable provisions of its regulations. The authorized installed capacity for such purposes is 6,000 horsepower.

            Article 28. Pursuant to Section 10(d) of the Act, after the first20 years of operation of the project under license, a specified reasonable rate of return upon the net investment in the project shall be used for determining surplus earnings of the project for the establishment and maintenance of amortization reserves. One half of the project surplus earnings, if any, accumulated after the first 20 years of operation under the license, in excess of the specified rate of return per annum on the net investment, shall be set aside in a project amortization reserve account at the end of each fiscal year. To the extent that there is a deficiency of project earnings below the specified rate of return per annum for any fiscal year after the first 20 years of operation under the license, the amount of that deficiency shall be deducted from the amount of any surplus earnings subsequently accumulated, until absorbed. One-half of the remaining surplus earnings, if any, cumulatively computed, shall be set aside in the project amortization reserve account. The amounts established in the project amortization reserve account shall be maintained until further order of the Commission.

            The annual specified reasonable rate of return shall be the sum of the annual weighted costs of long-term debt, preferred stock, and common equity, as defined below. The annual weighted cost for each component of the reasonable rate of return is the product of its capital ratio and cost rate. The annual capital ratio for each component of the rate of return shall be calculated based on an average of 13 monthly balances of amounts properly includable in the Licensee's long-term debt and proprietary capital accounts as listed in the Commission's Uniform System of Accounts. The cost rates for long-term debt and preferred stock shall be their respective weighted average costs for the year, and the cost of common equity shall be the interest rate on 10-year government bonds (reported as the Treasury Department's 10 year constant maturity series) computed on the monthly average for the year in question plus four percentage points (400 basis points).

            Article 29. Prior to commencement of any construction or development of any project works or other facilities at the project, the Licensee shall consult and cooperate with the Montana Historic Preservation Officer (SHPO) to determine the need for, and extent of, any archeological or historic resource surveys and any mitigative measures that may be necessary .The Licensee shall provide funds in a reasonable amount for such activity. If any previously unrecorded archeological or historic sites are discovered during the course of construction, construction activity in the vicinity shall be halted, a qualified archeologist shall be consulted to determine the significance of the sites, and the Licensee shall consult with the SHPO to develop a mitigation plan for the protection of significant archeological or historic resources. If the Licensee and the SHPO cannot agree on the amount of money to be expended on archeological or historic work related to the project, the Commission reserves the right to require the Licensee to conduct, at its own expense, any such work found necessary.

            (E) Within 90 days from the date of acceptance of this license, the Licensee shall file a statement under oath showing the gross amount of power generation for the project in kilowatt-hours for each calendar year commencing January 1, 1948, in accordance with the provisions of Section 11.20(a)(4) of the Commission's regulations.

            (F) This order is final unless a petition appealing it to the Commission is filed within 30 days from the date of its issuance, as provided in § 1.7(d) of the Commission's regulations, 18 C.F.R. 1,7(d) (1980). The filing of a petition appealing this order to the Commission or an application for rehearing does not operate as a stay of the effective date of this license or of any other date specified in this order, except as specifically ordered by the Commission. Failure of the Licensee to file an application for rehearing shall constitute acceptance of this license. In acknowledgment of acceptance of this license, the license shall be signed for the Licensee and returned to the Commission within 60 days from the date of issuance of this order.

–Footnotes–

1 Authority to act on this matter is delegated to the Director, Office of Electric Power Regulation, under 18 C.F.R § 375.308 (1980), as amended by 46 Fed. Reg. 14119(1981).

2 The U.S. Department of Agriculture, by letter of comment dated September 10, 1981, raised potential problems concerning a transmission line associated with this project. That line, however, is not a primary line and is not included as a project work in this license. Agriculture can take up its concerns directly with Licensee in the context of whatever special use permits are required to be obtained for the transmission line.

3 FPC v. Union Electric Company (Taum Sauk), 381 U.S. 90 (1965). .

4Farmington River Power Company v. FPC, 455 F. 2d 86 (2nd Cir. 1972).

5 Inspection, by the staff of the Commission, of the area between the dam and the Town of Troy confirms a low potential hazard as the topography provides a natural protection for the Town.

6See S.D. Warren, Project No.2897, Order Denying Rehearing (issued February 19. 1980).