|
The Lake Creek relicensing will be undertaken
using FERC's Integrated Licensing Process (ILP)
regulations. The first major step in the
ILP is the preparation of a
Pre-Application Document (PAD) to provide
FERC, agencies, and stakeholders with available information
pertaining to
the Project. To collect existing data and identify resource
issues, NLI held a series of
public meetings the week of July 10, 2005 to solicit
input. The final PAD, along with NLI's Notice of Intent
to relicense the Lake
Creek Project, was submitted to FERC on May 31, 2006. FERC
issued Scoping Document 1 (SD1)
on June 30, 2006 and held scoping meetings in Troy, MT on
August 9, 2006.
NLI filed a Proposed
Study Plan on October
13, 2006 and a revised Study
Plan on January 19, 2007.
FERC issued a Directors
Determination accepting the Study Plan on March 08,
2007. NLI filed its Initial Study
Report on November 30,
2007. After completing the required studies and analysis,
NLI will prepare a Draft
License Amendment.
If you have additional questions or comments
about relicensing, or would like to participate in the
process, please contact
LCrelicensing@norlight.org |